1. About 7 machines. The installation of air connectors, door sensors and angle adjustment of warning lights will be completed next time in Korea; 2. About 6 machines. Korean labels replacement, remote program modification, door sensors installation, hole blockage will also be completed next time in Korea. PS: The hole plugging materials for 6 machines had been sent out with 7, and the welding work on site needs to be completed by your engineers.3. We have no better plan to adjust the position of the safety sensors at present. Maybe we can discuss it when you come to YZM this month.4. Considering the workload of on the site next in Korea, we suggest that the working time should be set from January 6th to January 22nd.5. The nozzle drawings in DWG are being applied. If it is needed urgently, we can provide the PDF first.