GENERAL CONTRACTOR may terminate this Agreement and the employment of SUBCONTRACTOR, take possession of SUBCONTRACTOR's materials, tools and equipment used in performing such Work, and employ another Subcontractor or use the employees of GENERAL CONTRACTOR to finish the remaining Work to be performed hereunder. GENERAL CONTRACTOR may deduct the costs of completing the remaining work from the unpaid contract price, and if the cost of completing the remaining Work exceeds the unpaid Contract amount, SUBCONTRACTOR shall pay to GENERAL CONTRACTOR such excess costs, including but not limited to, overhead and cost of materials