During presentation PD sir put his observations and some instructions like below,- Anyhow 5 km pipe should be laid within September. For this contractors should be forced to select location where 4 dhara & local clearance is complete. - All supports like hot bending factory, cranes, authorized welder etc should be confirmed & checked by PMC ASAP before this 5 km laying. - Procurement progress of contractors should be more clear and expedite - Actual progress of land acquisition is not zero, data of the issue should be corrected more carefully - Most importantly he said PMC should realize the Bangladesh perspective. If they wait for 100% documentation then the project will never complete.