Please check following information! Today, only 5peoples of scaffolding are working on APL ML! Pump room there is no materials, no equipment, no scaffolding finished,and no access hole until today! I can’t complaining for this situation! But the progress is really slowly after ship alongside of jetty 8days! As I knowing, PX ocean shipyard only have 50-60peoples of scaffolding department!they working for all ships!